Update - November 2026

Project Scope

  • Preparation works including some minor vegetation trimming
  • Installation of new post and wire fence.
  • Construct a 2m wide concrete footpath including pram crossings.
  • Construct Kerb and Chanel adjacent to new footpath.
  • Installation of Recycled Bollards
  • New garden beds with plants and shrubs.
  • New Stormwater Drainage and pits
  • Retaining Wall
  • Minor road pavement works.
  • Road and Ped Crossings Line Marking

Please note, the scope only includes construction on the south side of Surf Parade.

Further investigations, design, costings and consultation with impacted property owners for the remaining streetscape are ongoing with a report due to Council in February 2027.

Pathway width

The new section of the Surf Parade Shared Path between Ozone Street and Goroke Street will be constructed at 2 metres wide, compared with the 2.5-metre width of previous sections.

The 2-metre width has been adopted to make the best use of the available road reserve while allowing for a possible future stage of the project to provide car parking and maintain two-way traffic on Surf Parade. Council is continuing feasibility, design and costing work for this future stage.

The 2-metre pathway meets applicable shared pathway standards and will provide a safe and connected link between the existing Surf Parade path and the Inverloch Surf Life Saving Club.

The narrower width also recognises the physical constraints along this section of Surf Parade, including the adjoining coastal reserve, where vegetation removal or encroachment into the reserve is not possible to accommodate the pathway.


Funding in the amount of:

Bass Coast Shire Council - $482k

Growing Suburbs Fund - $308k

Total - $790,000.00

What to expect

What to expect

  • Prior to work commencement, VMS boards will be placed at appropriate locations to advise changed traffic conditions.
  • Our contractors will advise each property via letter drop, in advance (generally within 2 days) of any works outside their property and will complete their works under traffic control with minimal delays and restrictions.
  • Construction of a 2-metre-wide concrete shared pathway between Ozone Street and Garoke Street (approx. 550 metres).
  • Construction of fencing, landscaping, retaining wall, minor drainage and pits, line marking and all other ancillary works.
  • Appropriate traffic/pedestrian detour measures will be in place throughout the duration of the works.
  • There will be some lane closures, with detours in place for traffic and pedestrians, this is for safety reasons during the construction works.
  • The use of plant and machinery including noisy works such as earthworks, power tools, saw cutting etc. and use of trucks delivering materials to the site.
  • Local Residents, School Buses and Rubbish Collection trucks will have access at all times.
  • There will be some lane closures, with detours in place for traffic and pedestrians, this is for safety reasons during the construction works.
  • The use of plant and machinery including noisy works such as earthworks, power tools, saw cutting etc. and use of trucks delivering materials to the site.

Site Plan

Site Plan

UPDATE - October 2026

UPDATE - 17 June 2026

UPDATE - 9 April 2026

UPDATE - 18 February 2026

UPDATE - 10 December 2025

UPDATE - 15 May 2024

Option 1 - Endorsed by Council 15 May 2024

Drawing showing one-way traffic and shared path on Surf Parade, Inverloch.

Option 1 - Endorsed by Council 15 May 2024

Consultation is now closed.

We sought your feedback on the two available options for construction of the final stage of a shared pathway on Surf Parade. The final (stage 3b) section is planned to continue from Ozone Street and finish at Goroke Street near the Surf Lifesaving Club. Thank you to all who provided feedback and to those who came to chat to our officers at our drop in sessions.

Consultation closed midnight, Sunday 8 October 2023.

Officers have reviewed all feedback and done further research following the results and a report will be considered by Council at its meeting on Wednesday, 15 May 2024.

Advice received from Department of Energy Environment and Climate Action

Statement by DECCA

Statement by DECCA