Bass Coast Shire Council wishes to advise the start of kerb renewal and drainage works along a section of Campbell Street in Wonthaggi. Super Paving Vic Pty Ltd has been appointed to undertake these works under an Annual Supply Contract.

The renewal of this section of Kerb and Drainage ensures that Council's road and drainage network is sustainable and be able to continue to provide appropriate levels of service for road users well into the future.

The total project cost is in the order of $25,000 which is funded through the Council’s adopted Capital Works Renewal Program 2022/23.

  • Removal and installation of approximately 50 metres of barrier kerb, drainage and associated works on the south side of the road, including some laybacks into driveways.
  • As part of these works, new concrete may be placed through landowner’s driveways. Access to properties will be restricted for a four-day period following from when the concrete kerb is poured. This is required to allow the concrete to set properly before any vehicles can use their driveway. Our Contractor will advise these landowners in advance, of any works affecting access to their properties.
  • Appropriate traffic and pedestrian control measures will be implemented onsite during these works. This will be a construction zone and we appreciate that for your own safety and others that access will be restricted. Our staff and contractor will notify nearby residents who may be impacted by these works.
  • The use of heavy plant and machinery including noisy and vibration works for construction including saw cutting, use of trucks for removal or delivery of materials.

Location of Works

Kerb Works

Kerb Works along Campbell Street, Wonthaggi