Project Update 26 October 2026

  • Temporary access track & crane pad installation completed.
  • Existing timber bridge deck & head stocks removal completed.
  • Glulam timber material arrived in Melbourne on 24 October.
  • Anticipated completion in early December subjected to favourable weather.

Project Update 01 October 2026

  • Glulam timber material is in transit and ETA in Melbourne on 19 October.
  • Melbourne Water Permit for works in the waterway has been received.
  • Site works has commenced.
  • Anticipated completion in early December subjected to favourable weather.

Map of Detour

detour route

Please note that access to properties will not be directly impacted. We apologise for the inconvenience to motorists and to the community affected by this detour, however Public Safety is our highest priority.

Progress Photos