About the Project

Bass Coast Shire has appointed Wiltrack Earthmoving Pty Ltd under our annual supply contract to carry out stormwater renewal and flood mitigation works along a section of Seaward Drive, Cape Paterson.

Construction is expected to start the last week of October 2023 with completion within 4 weeks, subject to favourable weather, material availability and contractor availability. These works are fully funded by Council as part of our stormwater renewal program in the order of $50,000.

The aim of this project is to improve storm water drainage system in the surround area. These works will reduce the chance of flooding from excess water during rain events.

These works are fully funded by Council as part of our stormwater renewal program in the order of $50,000.

  • Construction of a junction pit and extend 375mm diameter stormwater pipe.
  • Regrading the existing drain, rock protection, minor vegetation clearing and top soiling.
  • For safety reasons, this section of the street will be a construction zone. Appropriate traffic/pedestrian measures will be in place throughout the duration of the works.
  • The use of plant and machinery including noisy works such as earthworks and use of trucks delivering materials to site etc.
  • Please be aware that there will single lane closure during these works.

Location of Works

Location of Works